Projects

Watercare Services Ltd

Location: Auckland

Problem: Fabricate and install 600 NB (nominal bore) bypass in a 4-day window, then add a 6 m deep drainage sump.

Solution: Survey and model, then 3D detail the pipework. Generate shop drawings and fabricate, paint and assemble the pipe-work. Excavate the 6m sump and design temporary works to allow the pipe to be installed before the sump is backfilled. Plan the works every which way and go for it!

Far North District Council

Location: Kaitaia

Problem: Drought! Bore source requiring UV and clarifier treatment. Right now!

Solution: Portable clarifier and portable ThirstResponder UV unit.

Thames Coromandel District Council

Location: Hahei

Problem: Oxidation pond discharge to stream – consent renewal.

Solution: 600 m3/day self-contained EffBuster M unit.

Kaipara District Council

Location: Maungaturoto

Problem: Oxidation pond discharge to stream – consent renewal.

Solution: 1200 m3/day EffBuster M unit.

Watercare Services Ltd

Location: Pukekohe

Problem: High levels of iron (Fe) and manganese (Mn).

Solution: High chlorine dose to precipitate Fe and Mn, then removal with 4500 m3/day membrane filtration unit (ThirstResponder M).